Building a print log a structural reviewer will accept

Most print records are written for the team. A review record has a different reader and a different job.

A print log kept for the crew answers what happened. A print log for a reviewer has to answer whether the wall in front of them was built within the envelope the system was qualified to. Those are different documents.

The three logs that have to correlate

Hardware

Calibration state, nozzle condition and pump pressure across the print, timestamped so it can be aligned with the others.

Environment

Wind velocity, ambient moisture and mix temperature, sampled frequently enough to show variation across a long print rather than once at the start.

Execution against intent

Actual layer timing compared to the digital timeline. This is the audit that turns an assumption about open time into a measurement.

References

Standards, code provisions and peer-reviewed work this article rests on. Designations are given in full so a reviewer can pull the source themselves.

  1. ISO/ASTM 52939:2023Standard

    Additive manufacturing for construction — Qualification principles — Structural and infrastructure elements

    ISO / ASTM International · 2023

    The process standard: qualification principles, traceability and operational parameters for an additive construction site.

  2. ICC-ES AC509Standard

    Acceptance Criteria for 3D Automated Construction Technology for 3D Concrete Walls

    ICC Evaluation Service

    The product-side criteria: wall properties, fire resistance and structural testing, plus the quality documentation an evaluation requires.

  3. Buswell et al. (2018)Peer-reviewed

    3D printing using concrete extrusion: A roadmap for research

    R. A. Buswell, W. R. Leal de Silva, S. Z. Jones, J. Dirrenberger · 2018 · Cement and Concrete Research, 112, 37–49

    Frames the relationship between material behaviour, process control and the geometry you actually get.

Citing a standard is not the same as certifying compliance with it. Nothing here is engineering certification, legal advice or a code approval.